|
Metropolitan Water Reclamation District (MWRD) Board Meerting
July 16, 2026 The District’s second initiative to expand its Schoolyard Program to the Suburbs was approval by the Board to enter into an intergovernmental agreement with School District #104 and the Village of Summit for the design, construction, operation and maintenance of a “Space to Grow project” that would serve an elementary and a middle school. The cost for the District is projected at $3.6 million, and 775 thousand gallons of water are expected to be captured. #41 26-0487 #Davis thanked E.D. Murray for finding the money for this important project as the District has been struggling to identify funders. #Garcia suggested setting up a foundation for Space To Grow and other green projects. #Murray noted that a legislative change would likely be needed to set up the foundation ( It is expected to appear on the 2027 Legislative Priorities ) The Board agreed to the purchase order with IHC Construction for engineering design, construction, and installation services to Rebuild the Calumet’s Plant “Dewatering” facility at a cost not to exceed $82,225,000M. Due to the Chicago Transit Authority’s Red Line extension, trucking digested sludge from the lagoons to the drying beds is no longer practical. #18-260475 The Board also approved increasing an IHC contract by $31M to $15,597M for Phosphorus Removal Modifications at the O’Brien water reclamation plant. #27 65-0477 James Mohler, Executive Director of the MWRD Retirement Fund presented the 2025 Audit Results for the MWRD Retirement Fund. Below are highlights: #35 26-0464 *Market Value of Assets up by $240M over the last two years. Up to $1.79B *Net pension liability decreased by $173M over the last two years. *Over the last 7 years, the Fund’s cumulative net annual return of 8.8% exceeded the actuarial assumed rate of return of 7%. * Report assumes the board will remain focused on diversifying this portfolio to reduce risk. Trinity Christian College has leased 57 acres of MWRD land for athletic fields since 2008 but closed at the end of the 2026 school year. The board approved signing the lease over to Chicago Christian Schools at the current lease rent of $136,800. #40 26-0489 New Business Commissioner Brady-Davis asked for an update on the Harvey stormwater/flood control retention project. Ans: late 2026 for demolition; work starts in 2027 and finishes in 2028. When finished, 209 homes will be protected and 7.5 million gallons of water captured. Brady-Davis also asked what investment is needed in S. Suburban Cook County to prepare for the future. Ans: A feasibility study on this question will soon be ready. Executive Meeting: YES Deletions or Deferrals: NO Observer: Diane Edmundson
0 Comments
Metropolitan Water Reclamation District (MWRD) Board Meeting
June 18, 2026 Agenda Items
Observer - Peggy Kell MWRD Interim Inspector General Patrick Blanchard's term extended through December 31, 2026.6/21/2026 Metropolitan Water Reclamation District (MWRD) Board Meeting
June 4, 2026 Agenda Items
Deferred or Deleted Agenda Items
Observer: Peggy Kell Metropolitan Water Reclamation District (MWRD) Board Meeting
May 7, 2026 All agenda items were approved unanimously, other than one item which was deleted by the Executive Director: item 15, Authority to advertise a Contract to furnish and deliver janitorial supplies to various locations (#26-0324). There was quite a bit of discussion at today’s meeting, with the most centered around how to reach more municipalities with the Green Alley Program for which municipalities are invited to solicit projects to install permeable pavers to help alleviate stormwater run-off and flooding, which the MWRD will partially fund. The list of approved projects was discussed in the Observer Report for the April 16 meeting. At today’s meeting, the proposed intergovernmental agreements were on the agenda (items 34 to 41).
Another item that generated discussion was the item seeking authority for the MWRD to participate in the yearly WEFTEC (Water Environment Federation's Technical Exhibition and Conference) Operations Challenge. (Agenda item 31, #26-0291)
Other discussion included:
Time of meeting: 1 hour 45 minutes, including a 25-minute Executive Session. Observer: Priscilla Mims Metropolitan Water Reclamation District (MWRD) Board Meeting
April 16, 2026-10:30 A.M. Agenda Items: #12-26-0265- Commissioner Waller asked ED Murray to outline the current benefits of membership in CURRENT. ED Murray reported that MWRD was a founding member. Current concentrates on emerging technologies and work force development. The focus is on technical development. Our membership gives the MWRD a place on the resource consortium. The National Science Foundation has given funding to the organization and there is always the possibility that the MWRD can be a possible recipient of these grants. #23-26-0257- Commissioner Waller was pleased to see the MWRD was putting remaining BTU’s to use. ED Murray said that the MWRD uses all the energy during the winter months. He said that he would be happy to give a full report to the Board on savings. As to whether the MWRD can reach energy neutrality, the District uses a lot of energy to pump water out of the two deep tunnels. Also an aging infrastructure impacts energy use. #30-26-0260- Report on the Green Infra-structure: Commissioner Kirkwood asked if the MWRD reached out to every municipality. Murray said yes. What are the requirements to participate?
Commissioner Davis asked how the work with disproportionately impacted communities is going? Murray replied that there are two staff members (one a civil engineer) helping with outreach and that it is working pretty well. President Steele agreed. Commissioner Davis asked if the “technical assistance” has resulted in the creation of successful projects. ED Murray committed to getting more information on this to the Board. Deferred or Deleted Agenda Items- Three items deferred from the April 2 Board meeting were not mentioned at the April 16 meeting. They are agenda items #4,6, & 7. #4-26-0235- Authorization to revise Contract Change Order Policy for Capital Improvement Construction Projects. #6-26-0216- Authority to advertise Contract 26-023-11. Furnish and Deliver Lab Chemicals to various locations. #7-26-0217- Authority to advertise Contract to Furnish Deliver Stem Gate Valves to Various Locations for One Year. These items were all deferred at the April 2 meeting by Commissioner Garcia, who was absent from the April 16, 2026 board meeting. New Business:
Summary of Requests for more information from the Executive Director:
Observer: Georgia Gebhardt Meeting Length - 40 minutes No Executive Session Metropolitan Water Reclamation District (MWRD) Board Meeting
April 2, 2026; 10:30 a.m. Board Discussion and Action: Commissioner Garcia raised the issue of the difficulty of finding minority women vendors. He asked if the MWRD was reaching out to vendors outside of the agency’s data base. Staff replied that they also review data bases from the City of Chicago and found no firms that fit the need. Commissioners asked if staff reached out to Cook County and to the State. It was suggested that perhaps they needed to reach beyond the virtual to identify vendors. Commissioner Corral-Sepulveda asked about certification activity and about how MWRD determines how far to reach out for vendors. She asked if contractors can be certified after the contract has been adopted. Staff said yes, this “rolling” certification can be done. Commissioner Garcia asked that there be better reporting of the numbers and the process. President Steele requested ED Murray to include all the questions/answers on this subject in an email to the commissioners. She also reminded the commissioners that they should send their questions through the Executive Director. He will then direct them to the appropriate staff for response. #5-0212 Commissioner Kirkwood asked why polymer is crucial. ED Murray explained that it is used in sludge thickening, separating water and solids in the production of cake. Commissioner Waller asked if this expenditure would be required if the Red Line extension was not happening and could the MWRD recover any costs from the CTA. Murray answered that there would be no reimbursement. He explained that they would use pumps to pump sludge into a geo-pool where it settles out in fifteen days. Centrifuges are much quicker. Centrifuges are expected to be online by 2028. #8-26-0222 Commissioner Brady-Davis expressed appreciation that the Harvey Sewer Improvements project was getting underway. This is an 18-month project. She asked how this is being communicated to the citizens of Harvey. Staff replied that communication is hard-wired into every contract. Several commissioners asked for assurance that this communication would be happening and indeed, that those involved should “over communicate” to the citizens. Commissioner Garcia asked if there were any budgetary issues in Harvey. Murray replied that the capital funding was through grant money. Harvey is only responsible for the ongoing maintenance after project completion. #9-26-0225 Comm. Garcia Deferred Agenda Items: # 4,6,7 All dealing with inability to find minority contractors due to specifics of need. Duration of Meeting: 66 minutes Executive Session: No Observer: Georgia Gebhardt |
AuthorIndividual authors are credited at the end of each report. Archives
July 2026
Categories
All
|
RSS Feed